Question

Which of the following is the critical path in the picture shown below?
A. A, C, F
B.

A, D

C.

B, E

D.

Both A and B

Show Answer

Correct Answer � A

Explanation

Ans.  ‘A’ i.e., A, C, F

 A critical path is determined by identifying the longest stretch of dependent activities and measuring the time required to complete them from start to finish.

  •  The critical path is the longest path.
  •  In the figure, the longest path is A → C → F (taking 7 weeks in total).