Question
Which of the following is the critical path in the picture shown below?
| A. | A, C, F |
| B. |
A, D |
| C. |
B, E |
| D. |
Both A and B |
Show Answer
|
Correct Answer � A Explanation |
|
Ans. ‘A’ i.e., A, C, F
A critical path is determined by identifying the longest stretch of dependent activities and measuring the time required to complete them from start to finish.
- The critical path is the longest path.
- In the figure, the longest path is A → C → F (taking 7 weeks in total).
