Question
Which of the following is the critical path in the picture shown below?
| A. |
A, C, F
|
| B. |
A, D
|
| C. |
B, E
|
| D. |
Both A and B
|
Show Answer
|
Correct Answer � A
Explanation
|
|
Ans. ‘A’ i.e., A, C, F
A critical path is determined by identifying the longest stretch of dependent activities and measuring the time required to complete them from start to finish.
- The critical path is the longest path.
- In the figure, the longest path is A → C → F (taking 7 weeks in total).